| July/August 2008 |
Drainage, kerb and paving, multi utilities installations |
|
| March 2008 |
Commence installation of culvert units and drainage infrastructure |
|
| February 2008 |
Complete statutory diversions of electricity, gas and water through site. |
|
| January 2008 |
Removal of contaminated land to hazardous waste facility |
|
| December 2007 |
Lime stabilisation works to improve the strength of existing soils
|
|
| November 2007 |
Earthworks continue with remediation and ground improvements |
|
| October 2007 |
Mobilisation on site and commencement of soil strip and earthworks |
|
| September 2007 |
Construction phase commenced |
|
| August 2007 |
Funding confirmed |
|
| March/April 2007 |
Planning approval confirmed |
|
| October 2006 |
Trial for ground improvement technique |
|
| August/September 2006 |
Catching and relocating reptiles |
|
| July 2006 |
Erection of Reptile Fence |
|
| July 2006 |
Carillion were appointed Main Contractor to undertake Early Contractor Involvement for the Project |
|
|
|
|