The Waterfront
  : : home : : : : news : : : : scheme overview : : : : scheme progress : : : : project team : : : : FAQ's : : : : local opportunities : : : : contacts : :
scheme progress
Activities for July 2008/August 2008
  • Surfacing works are largely complete
  • Vibropiling commenced the stone column installation works
  • Street lighting works are progressing well
  • fencing and landscaping activities are underway
  • Walney Channel Outfall Structure is now complete
 
Night works
   
 
 
   
   
July/August 2008 Drainage, kerb and paving, multi utilities installations
March 2008 Commence installation of culvert units and drainage infrastructure
February 2008 Complete statutory diversions of electricity, gas and water through site.
January 2008 Removal of contaminated land to hazardous waste facility
December 2007 Lime stabilisation works to improve the strength of existing soils
November 2007 Earthworks continue with remediation and ground improvements
October 2007 Mobilisation on site and commencement of soil strip and earthworks
September 2007 Construction phase commenced
August 2007 Funding confirmed
March/April 2007 Planning approval confirmed
October 2006 Trial for ground improvement technique
August/September 2006 Catching and relocating reptiles
July 2006 Erection of Reptile Fence
July 2006 Carillion were appointed Main Contractor to undertake Early Contractor Involvement for the Project
Constructing Excellence Demonstration Project Programme
please click on any of the logos above to take you directly to the company's websites
Constructing Excellence Demonstration Project Programme Cumbria County Council Centre for Construction Innovation Capita Symonds Alfred McAlpine plc Furness Enterprise West Lakes Renaissance Capita Symonds Centre for Construction Innovation West Lakes Renaissance